Project for rehabilitation and expansion of the main desalination plant
Awarded toAward date (estimated): 2023-01-30
Award value2,555,556 SAR
Bid amount2,555,556 SAR
Project ended around2023-10-06
Contract term240 days
The project period depends on the site handover or start approval date, so this is an estimate that varies by agency and project
Submitted Bids 8
| Company | Bid amount | Result |
|---|---|---|
| Wabra | 2,555,556 SAR | Winner |
| Samnan | 4,415,784 SAR | Bidder |
| Miyah for Water and Environment Technology Company | 4,324,546 SAR | Bidder |
| UUES | 3,413,631 SAR | Bidder |
| Taameed Co. Ltd. (One-Person Co.) | 3,373,813 SAR | Bidder |
| AWS | 3,326,674 SAR | Bidder |
| Nawat Saudi Water Technology Co. (One-Person Co.) | 2,984,943 SAR | Bidder |
| Bait Al Murooj Contracting Co. (One-Person Co.) | 2,750,731 SAR | Bidder |
Tender Details
- Government agency
- Royal Saudi Land Forces
- Tender type
- Public Tender
- Tender number
- 2023/32
- Reference number
- 221239853678
- Branch
- King Fahd Military City Administration, Eastern Province
- Region
- Eastern Province
- Contract term
- 240 days
- Published
- 2023-01-08
- Bid deadline
- 2023-01-30
- Bid opening date
- 2023-01-30
- Status
- Awarded