Maintenance and rehabilitation of the central services walkway (phase 2)
Awarded toAward date (estimated): 2023-01-19
Award value4,191,744 SAR
Bid amount4,191,744 SAR
Project ended around2023-11-19
Contract term8 months
The project period depends on the site handover or start approval date, so this is an estimate that varies by agency and project
Submitted Bids 8
| Company | Bid amount | Result |
|---|---|---|
| Al Durra Al Mutamayyiza General Contracting Co. | 4,191,744 SAR | Winner |
| Dhawan Co. Ltd. | 10,994,000 SAR | Bidder |
| Akasim | 9,026,327 SAR | Bidder |
| Fajr Al Qunfudhah Contracting Est. | 8,681,300 SAR | Bidder |
| Raad Al Sharq Contracting Co. (One-Person Co.) | 8,345,849 SAR | Bidder |
| Wadi Al Ikhwa Contracting Co. | 5,810,295 SAR | Bidder |
| Hamed Abdulghani Al Zubaidi Contracting Co. | 5,582,894 SAR | Bidder |
| Akan Middle East | 4,777,871 SAR | Bidder |
Tender Details
- Government agency
- Al-Qouz Municipality (Al-Qunfudhah)
- Tender type
- Public Tender
- Tender number
- 90
- Reference number
- 221239856730
- Branch
- Al-Quz Municipality
- Region
- Makkah Region
- Contract term
- 8 months
- Published
- 2022-12-26
- Bid deadline
- 2023-01-18
- Bid opening date
- 2023-01-19
- Status
- Awarded