Rehabilitation of King Abdullah Primary and Intermediate School building (boys)
Awarded toAward date (estimated): 2023-02-07
Award value527,275 SAR
Bid amount527,275 SAR
Project ended around2023-09-03
Contract term180 days
The project period depends on the site handover or start approval date, so this is an estimate that varies by agency and project
Submitted Bids 8
| Company | Bid amount | Result |
|---|---|---|
| Abdullah Saeed Bahloul Al Mufarrij Contracting Est. | 527,275 SAR | Winner |
| Asrab Al Khaleej Contracting Est. | 734,045 SAR | Bidder |
| Al Binaa Al Muntathim Engineering Consultants Co. | 649,750 SAR | Bidder |
| Abdulrahman Yahya Abdulrahman Al Zahrani Contracting Est. | 579,525 SAR | Bidder |
| Tatweer Arabian Contracting Est. | 569,710 SAR | Bidder |
| Jumaan Mohammed Al Omari General Contracting Est. | 568,755 SAR | Bidder |
| Majed Abdullah Al Shehri Contracting Est. | 546,940 SAR | Bidder |
| Soor Al Najah General Contracting Co. | 333,980 SAR | Bidder |
Tender Details
- Government agency
- Al-Namas Education Department
- Tender type
- Public Tender
- Tender number
- 34/44/102
- Reference number
- 230139874054
- Branch
- Al-Namas Education Department Branches
- Region
- Asir Region
- Contract term
- 180 days
- Published
- 2023-01-22
- Bid deadline
- 2023-02-06
- Bid opening date
- 2023-02-07
- Status
- Awarded