Asphalting, sidewalks and lighting (lighting and sidewalks) for Al-Nabhaniyah Governorate Municipality
Awarded toAward date (estimated): 2023-04-30
Award value2,743,785 SAR
Bid amount2,743,785 SAR
Project ended around2024-02-26
Contract term300 days
The project period depends on the site handover or start approval date, so this is an estimate that varies by agency and project
Submitted Bids 13
| Company | Bid amount | Result |
|---|---|---|
| Dara Contracting Co. (One-Person Co.) | 2,743,785 SAR | Winner |
| شركة ابداع الحياة للإستثمار | 12,448,750 SAR | Bidder |
| Bawabat Al Fajr Contracting Est. | 7,319,980 SAR | Bidder |
| Masar Al Remal | 5,998,975 SAR | Bidder |
| Abdulrasheed Mohammed Faidallah Contracting Est. | 5,928,250 SAR | Bidder |
| Saleh Abdulrahman Al Luhaidan Contracting Co. | 5,342,000 SAR | Bidder |
| Aamal Al Aqd Contracting Co. | 5,057,614 SAR | Bidder |
| Wadi Harib Contracting Co. | 4,421,175 SAR | Bidder |
| Hashas Contracting Est. | 3,967,241 SAR | Bidder |
| Abdullah Ali Al Awad Contracting Est. | 3,936,500 SAR | Bidder |
| Deqat Altakhtit Contracting | 3,843,185 SAR | Bidder |
| Wadi Al Ikhwa Contracting Co. | 3,603,410 SAR | Bidder |
| Majd Al Umma General Contracting Est. | 2,817,500 SAR | Bidder |
Tender Details
- Government agency
- Al-Nabhaniyah Governorate Municipality
- Tender type
- Public Tender
- Tender number
- 41
- Reference number
- 230439935980
- Branch
- Al-Nabhaniyah Municipality
- Region
- Qassim Region
- Contract term
- 300 days
- Published
- 2023-04-05
- Bid deadline
- 2023-04-27
- Bid opening date
- 2023-04-30
- Status
- Awarded