Supply and earth levelling works at Al-Dughmiyah plan in Al-Khurmah Governorate
Awarded toAward date (estimated): 2023-05-16
Award value93,150 SAR
Bid amount93,150 SAR
Project ended around2023-08-19
Contract term90 days
The project period depends on the site handover or start approval date, so this is an estimate that varies by agency and project
Submitted Bids 11
| Company | Bid amount | Result |
|---|---|---|
| Sitti Thamanoon General Contracting Est. | 93,150 SAR | Winner |
| Watad Advanced Co. Ltd. | 563,937 SAR | Bidder |
| Reen Naif Mohammed Al Shahrani General Contracting Est. | 381,225 SAR | Bidder |
| Haya Mufarreh Bin Shabab Al Subaie Contracting Est. | 379,500 SAR | Bidder |
| Mahawir Al Mudun General Contracting Est. | 345,000 SAR | Bidder |
| Al Badi Contracting Co. | 341,550 SAR | Bidder |
| Eid Abdullah Bin Eid Al Otaibi Contracting Est. | 299,805 SAR | Bidder |
| Rawabi Quba Contracting Est. | 241,500 SAR | Bidder |
| Taameer Al Jazira Contracting Co. | 241,500 SAR | Bidder |
| Nasser Thaar Thamer Al Subaie General Building Contracting Est. | 224,250 SAR | Bidder |
| Itlala Al Jawda Trading Est. | 182,747 SAR | Bidder |
Tender Details
- Government agency
- Al-Khurmah Governorate Municipality
- Tender type
- Direct Purchase
- Reference number
- 230539956404
- Branch
- Al-Khurmah Governorate Municipality
- Region
- Makkah Region
- Contract term
- 90 days
- Published
- 2023-05-10
- Bid deadline
- 2023-05-16
- Status
- Awarded