Upgrade of the monitoring and control system of the water treatment plant at the Khobar 3 production system
Awarded toAward date (estimated): 2024-08-28
Award value194,331 SAR
Bid amount194,331 SAR
Project ended around2024-11-15
Contract term2 months
The project period depends on the site handover or start approval date, so this is an estimate that varies by agency and project
Submitted Bids 1
| Company | Bid amount | Result |
|---|---|---|
| Al Hulool Comprehensive Equipment Maintenance & Automation Co. Ltd. | 194,331 SAR | Winner |
Tender Details
- Government agency
- Saudi Water Authority
- Tender type
- Public Tender
- Tender number
- 707006
- Reference number
- 240839003192
- Branch
- Khobar Production System
- Region
- Eastern Province
- Contract term
- 2 months
- Published
- 2024-08-07
- Bid deadline
- 2024-08-28
- Bid opening date
- 2024-08-28
- Status
- Awarded