Maintenance and rehabilitation of the main stadium in Al-Ajfar (phase 1) to address visual distortion
Awarded toAward date (estimated): 2024-09-05
Award value654,649 SAR
Bid amount654,649 SAR
Project ended around2025-01-03
Contract term120 days
The project period depends on the site handover or start approval date, so this is an estimate that varies by agency and project
Submitted Bids 12
| Company | Bid amount | Result |
|---|---|---|
| Tashkeel Plus Co. Ltd. | 654,649 SAR | Winner |
| Imdad Al Hulool Contracting Co. | 2,489,175 SAR | Compliant |
| Ehkam | 1,577,352 SAR | Compliant |
| Al Wafaa United Co. Ltd. | 1,561,240 SAR | Compliant |
| Rasmco | 1,325,375 SAR | Compliant |
| Qimam Al Injaz Al Omrani Contracting Est. | 1,231,282 SAR | Compliant |
| Shurooq Al Taameer General Contracting Co. | 1,115,109 SAR | Compliant |
| Abraj Al Tayyar Contracting Est. | 996,245 SAR | Compliant |
| Aali Al Mustaqbal Contracting Co. | 876,714 SAR | Compliant |
| Fadaa Al Janoub Contracting Est. | 679,880 SAR | Compliant |
| Al Muhtarifoon Al Fanniya General Contracting Est. | 949,808 SAR | Non-compliant |
| Al Watad Al Hirafiya General Contracting Est. | 833,532 SAR | Non-compliant |
Tender Details
- Government agency
- Hail Region Municipality
- Tender type
- Public Tender
- Tender number
- 2024-24/ع
- Reference number
- 240839010087
- Branch
- Al-Ajfar Municipality
- Region
- Hail Region
- Contract term
- 120 days
- Published
- 2024-08-20
- Bid deadline
- 2024-09-05
- Bid opening date
- 2024-09-05
- Status
- Awarded