Rehabilitation and painting at the Nabi Dama charitable desalination plant of the Duba production unit
Awarded toAward date (estimated): 2024-11-27
Award value74,463 SAR
Bid amount74,463 SAR
Project ended around2025-01-30
Contract term60 days
The project period depends on the site handover or start approval date, so this is an estimate that varies by agency and project
Submitted Bids 7
| Company | Bid amount | Result |
|---|---|---|
| Al Ruaa Al Rabia Contracting Co. | 74,463 SAR | Winner |
| Mohammed Ibrahim Ahmed Al Udaisani General Contracting Est. | 141,853 SAR | Compliant |
| Abraj Omar Contracting Co. (One-Person Co.) | 132,193 SAR | Compliant |
| Fatima Ibrahim Hamed Ajwa Contracting Est. | 91,287 SAR | Compliant |
| Al Sarh Al Qaim Contracting Est. | 89,528 SAR | Compliant |
| Alwan Plus Trading Est. | 60,571 SAR | Compliant |
| Al Taameer Al Hadari Contracting Est. | 739,450 SAR | Non-compliant |
Tender Details
- Government agency
- Saudi Water Authority
- Tender type
- Direct Purchase
- Tender number
- 705630
- Reference number
- 241139008467
- Branch
- Yanbu Production System
- Region
- Tabuk Region
- Contract term
- 60 days
- Published
- 2024-11-14
- Bid deadline
- 2024-11-27
- Status
- Awarded