Maintenance of vertical lifts at the third reverse osmosis plant in the Jeddah seawater desalination system
Awarded toAward date (estimated): 2025-10-16
Award value195,500 SAR
Bid amount195,500 SAR
Project ends around2027-10-22in 11 months
Contract term24 months
The project period depends on the site handover or start approval date, so this is an estimate that varies by agency and project
Submitted Bids 3
| Company | Bid amount | Result |
|---|---|---|
| Prime Source Group | 195,500 SAR | Winner |
| Elaf Al Mudun Operation & Maintenance Co. | 511,750 SAR | Compliant |
| شركة الخدمات البحريه المحدودة | 284,696 SAR | Compliant |
Tender Details
- Government agency
- Saline Water Conversion Corporation (SWCC)
- Tender type
- Public Tender
- Tender number
- 203954
- Reference number
- 250939014537
- Branch
- Jeddah Production System
- Region
- Makkah Region
- Contract term
- 24 months
- Published
- 2025-09-30
- Bid deadline
- 2025-10-16
- Bid opening date
- 2025-10-16
- Status
- Awarded